Development Approval vs Building Approval in Queensland
Two different approvals, two different assessors, two different timeframes — and why confusing them is one of the most common causes of program delay.
They are not the same thing
Clients frequently use the phrase "council approval" as though it describes a single event. In Queensland it usually describes two separate processes, assessed against different criteria, often by different people, on different timeframes.
Development approval is about land use and planning. Building approval is about construction standards. You can hold one and still be unable to start.
Understanding which your project needs, and in what order, is the difference between a program that runs and one that stalls for months.
Development approval: can you do this here?
Development approval is assessed against the local planning scheme — Brisbane City Plan, Gold Coast City Plan, the Logan, Ipswich or Sunshine Coast schemes, and so on. It considers whether the proposed use and built form are acceptable at that location.
Zone, density, height, setbacks, site cover, private open space, car parking, overlays and streetscape all get assessed here. A single dwelling on a straightforward suburban block frequently does not need one. A dual occupancy usually does. Work in a character overlay generally does.
The critical distinction within development approval is whether the proposal is code assessable or impact assessable. Code assessable proposals are measured against the relevant codes. Impact assessable proposals go to public notification, which means neighbours can make submissions, and submissions carry appeal rights. That difference can add months.
Building approval: is it built properly?
Building approval is assessed against the National Construction Code and the relevant Australian Standards. It considers structural adequacy, fire safety, health and amenity, energy efficiency, and access.
In Queensland this is generally handled by a private building certifier rather than the council. The certifier issues the approval, carries out mandatory inspections at defined stages, and issues the final certificate at completion.
Building approval cannot be issued in a way that conflicts with a development approval. If your project needs both, the development approval comes first, and the building approval must be consistent with it.
The other approvals people forget
Plumbing and drainage work generally requires its own approval and inspections. Demolition may need approval in its own right, and in a character area that approval is far from guaranteed.
Operational work — earthworks, retaining above certain heights, vegetation clearing, driveway crossovers — can require separate approval depending on the scheme and the site.
In a Priority Development Area, such as the Ripley Valley near Ipswich, the assessment runs under a development scheme administered by Economic Development Queensland rather than the council entirely. Different rules, different process.
How to keep the program moving
Establish early which approvals your project actually needs, and whether the development application is code or impact assessable. That single question drives your program more than any other.
Get the site information — survey, soil test, property report — before design, because information requests during assessment are a common and entirely avoidable cause of delay.
Do not sign a construction contract with a start date that assumes an approval you do not yet hold. And do not let anyone start work that requires an approval that has not issued, because unapproved work has to be either approved retrospectively or removed.